Status and Schedule

Data refreshes automatically every 5 minutes. Click an image to enlarge.
Recent Status Messages
Tue, 12 Aug 2008 20:45:08 Beam Motion
On Tuesday August 12, 2008 from 20:24 to 20:26 Storage Ring Horizontal and Vertical RMS Motion and Emittance spiked. At this time there is no known reason for the spike. It was not due to the CPU nor due to movement of ID gaps.
Sun, 10 Aug 2008 05:24:26 Shutter Permit enabled
At 05:16 Shutter Permit was enabled with 102mA stored and TopUp running. The repair of the SR DCCT [DC Current Transformer] has been completed and the necessary validations performed.
Sun, 10 Aug 2008 01:25:16 SR DCCT failures
At 22:29 Diagnostics personnel are continuing to investigate the root cause of the failures. This will require accessing the SR Tunnel, and everything is in place for that happen. Another email will be sent when more details are available. In the meantime, please check the message board for interim updates.
Sat, 09 Aug 2008 20:06:50 Shutters Enabled
On 8/9/8 at 12:55 stored beam was lost due to a failed SR DCCT. Its PCT chassis was replaced. The needed safety validations were performed. Shutter permit was enabled on 8/9/8 at 19:35.
Sat, 9 Aug 2008 17:16:56 Beam Loss/Investigation
Beam Loss/Investigation On Saturday, August 9th, 2008 at 12:55PM stored beam was lost. The SR MPS system indicated SR current over max. The SR S35:DCCT is giving a false readback, and Diagnostics group personnel are enroute to investigate. The next fill time has not been established pending further investigation/repair. ASD-Operations XRAYOPS at mailman.aps.anl.gov
Sat, 9 Aug 2008 17:16:43 Beam Loss/Investigation
Beam Loss/Investigation On Saturday, August 9th, 2008 at 12:55PM stored beam was lost. The SR MPS system indicated SR current over max. The SR S35:DCCT is giving a false readback, and Diagnostics group personnel are enroute to investigate. The next fill time has not been established pending further investigation/repair. ASD-Operations XRAYOPS at mailman.aps.anl.gov
Sat, 09 Aug 2008 14:24:20 Beam Loss/Investigation
On Saturday, August 9th, 2008 at 12:55PM stored beam was lost. The SR MPS system indicated SR current over max. The SR S35:DCCT is giving a false readback, and Diagnostics group personnel are enroute to investigate. The next fill time has not been established pending further investigation/repair. ASD-Operations
Sat, 9 Aug 2008 08:12:09 IOC problem resolved
The problem with IOCS17VP that was requiring TopUp & controllaw aborts has been resolved.
Sat, 9 Aug 2008 05:44:47 Ongoing IOC reboots
We are continuing to investigate a communications issue with a SR vacuum and PS equipment IOC. So far, this IOC has been rebooted and power-cycled to faciliate the investigation and repair. Shortly, a card in the IOC will be replaced which will require another power-cycle. Announcements will continue to be made when TopUp and Orbit Correction are aborted and restarted. Another email will be sent when the problem has been resolved.
Thu, 7 Aug 2008 21:09:54 Top-up and SR controllaws aborted.
On 07 AUG 08 at 08:48 communications were lost with IOCS25FB. Top-up was aborted and the SR orbit controllaws were aborted at 20:52 to facilitate the reboot of the IOC. At 21:00 the controllaws were restarted and top-up was restarted.
Thu, 7 Aug 2008 07:21:18 Top-Up aborted
At 07:09 on 08/07/08 Top-Up has been aborted due to a problem with one of the injectors. Investigation into the problem is underway.
Wed, 06 Aug 2008 15:16:33 Top-up has been restarted
The injector IOC problem has been resolved and Top-up has been restarted.
Wed, 06 Aug 2008 15:12:20 Top-up aborted
Top-up has been aborted at 14:56 due to an Injector IOC problem. The Controls Group is currently investigating the problem.