STATUS
+ Current Status
+ Recent
   Accomplishments
+ What's Next?
spacer
NEWS
spacer
ABOUT THE WEBB
spacer
SCIENCE
spacer
INSTRUMENTS
spacer
FEATURES
spacer
IMAGES & VIDEOS
spacer
MEET THE TEAM
spacer
FOR SCIENTISTS
spacer
FOR EDUCATORS
spacer
FOR PRESS
spacer


RSS news feed RSS
Twitter Twitter
Facebook Facebook
YouTube channel YouTube
Flickr Flickr
Gplus G+


Recent Accomplishments

Updated February 6, 2013

The following list contains a record of program and project accomplishments for the James Webb Space Telescope.  The left column gives the original due date, the middle column gives the item accomplished, and the right column indicates the schedule performance with green text denoting items accomplished earlier than planned, black text for items completed on schedule, and red text for items finishing later than planned. The list will be updated approximately every month.  

The image below points out various major hardware components of the facility referred to in the list to orient the reader. (Click to enlarge image.)

Labeled Spacecraft

 

Due Date
Item Accomplished
Completion Date

February 2013

Secondary Mirror Support Structure I&T tooling fixture complete

Primary mirror backplane support wing assemblies complete

Spacecraft Primary Structure Manufacturing Readiness Review

Start cryogenic certification test of OSIM

 

 

 

January 28, 2013


Moved to March 2013 - delayed by Global Precipitation Monitor exit from SES chamber

January 2013

Aft optical system complete

Receive JWST carrier container to be used in moving the observatory to testing and launch sites

System design review of the software employed in managing all the data returned from the spacecraft to the operations center

Deliver MIRI cover/thermal shield to ISIM integration and test (I&T;)

January 10, 2013

November 16, 2012


December 6, 2012


Dynamics and Thermal issue have delayed delivery to March, Two weeks of schedule margin still exists to need date

December 2012

First engineering model of the spacecraft command and telemetry computer delivered to test bed

Reinstall beam image analyzer onto telescope simulator (OSIM) used in ISIM cryogenic testing

Complete electrical checkout of combined fine guidance sensor (FGS) and ISIM

November 8, 2012



December 19, 2012


December 20, 2012


November 2012

Spacecraft-to-Optical Telescope Element/science instruments stray light and thermal barrier structures preliminary design review

Port side spacecraft equipment panel design review (Northrop internal review)

Complete electrical checkout of combined mid-infrared instrument (MIRI) and integrated science instrument module (ISIM)

October 18, 2012

 

October 4, 2012


November 19, 2012. 2 days of testing required in Jan. due to FSW bug (divide by zero)

October 2012

Headquarters delivery to project of funding plan for fiscal 2013

Spacecraft batteries preliminary design review

Spacecraft command & telemetry computer review (Northrop internal review)

Second review of optical test equipment for Johnson Space Center (JSC) thermal vacuum chamber test of telescope and instruments (OTIS)

September 15, 2012


September 6, 2012

August 30, 2012


October 17, 2012

September 2012

Deliver NIRCam

 



Start testing of cryogenic camera system, used for subsequent JSC I&T;

Complete center section of Backplane Support Structure for main mirror

Deliver NIRSpec

Moved to no earlier than 12/2012, work around in place
Delivery no later than August 2013

August 9, 2012


April 28, 2012


Delivery date April 2013Delivery no later than September 2013

August 2012

Order remaining JSC thermal vacuum chamber vibration isolators

August 9, 2012


July 2012

Deliver Flight Fine Guidance Sensor

Deliver flight software to ISIM Integration and Testing ("ISIM I & T")

Complete Solar array Preliminary Design Audit

Deliver MIRI Cryo Cooler "Cold Head Assembly" (critical component of MIRI cooling) to ISIM I&T


Complete fabrication of end fitting for Secondary Mirror Support Structure

July 30, 2012

May 11, 2012

June 14, 2012

Flight CHA to be delivered in June 2013. No schedule, impact, work around in place.

July 13, 2012

June 2012

Complete modifications of the Johnson Space Center (JSC) Thermal Vacuum Chamber (TVC).

Complete Critical Design Review for telescope-ground communications system.

Complete designs for structures that will hold telescope inside JSC TVC.

Complete Preliminary Design Review for equipment that tests Sunshield deployment.

June 30, 2012


June 13, 2012


June 21, 2012


June 28, 2012

May 2012

Finish testing the COCOA

Measure Sunshield template layer 5 shape to confirm its accuracy

Conduct budget and schedule review of replanned program and project performance

March 9, 2012

April 23, 2012


May 30, 2012

April 2012

Complete all composite parts for mechanism that lifts telescope away from spacecraft after launch (Deployable Tower Assembly)

Receive MIRI from Europe (extra vibration test delay)

February 28, 2012, completed two months early

May 29, 2012

March 2012

Deliver ISIM computer #2 to ISIM integration and testing. (Single synchronous dynamic random access memory chip failure during computer thermal vacuum testing. Chip is being replaced and computer retested. )

Complete analysis of JSC Thermal Vacuum Chamber telescope testing equipment plans

System Engineering Team to complete assessment of instrument thermal margins

Delivery of 2nd ISIM computer to Integration and Test

May 15, 2012

 



March 19, 2012


March 1, 2012


May 16, 2012

February 2012

Install Helium shroud walls at JSC Thermal Vacuum Chamber

Complete assembly and initial testing of main mirrors at Marshall Space Flight Center

February 2, 2012, (all panels, walls, floor, ceiling, door)

December 19, 2011, Completed two months early

January 2012

Conduct Critical Design Review for Spacecraft-to-Optical Telescope Element vibration isolation system

Finish building Center of Curvature Optical Assembly ("COCOA") for testing primary mirror in JSC TVC

Review preliminary requirements for ground structure for spacecraft equipment panels


Complete Aft Optic System integration and alignment

December 15, 2011, Completed one month early

January 19, 2012



December 1, 2011, Completed one month early

December 2, 2011, Completed one month early

December 2011

Install Helium shroud floor at Johnson Space Center thermal vacuum chamber ("JSC TVC")


Determine root cause of NIRSpec optical bench flaw

October 27, 2011 Completed two months early

December 15, 2011

November 2011

Complete electronics simulator model for Integrated Science Instrument Module ("ISIM")

Deliver tools for software development environment and verification

November 15, 2011


October, 27, 2011 Completed one month early

September 2011

Deliver Flight ISIM Electronics Compartment to ISIM Integration & Test

Deliver flight ISIM Command & Data Handling unit #1 to ISIM Integration & Test

August 2012


September 27, 2011

August 2011

Spacecraft Flight Software Build 1 Technical Readiness Review

June 30, 2011, Completed two months early

July 2011

Deliver ISIM Region 1 Wiring Harnesses

Deliver ISIM Structure to ISIM Integration & Test

July 22, 2011

July 28, 2011

June 2011

Complete Common Command & Telemetry System Build 2.3

Start ISIM level Integration & Test

April 13, 2011, Completed two months early

June 24, 2011

May 2011

Start flight Fine Guidance Sensor environmental testing (instrument level)

Complete Spacecraft Secondary Mirror Segment Cone Structure internal Design Review

May 5, 2011


April 20, 2011 Completed one month early

April 2011

Pathfinder Primary Mirror Segment Assemblies complete

Deliver ISIM Command & Data Handling test unit to ISIM Integration & Test

Complete 2018 Launch Readiness Date project lead Joint cost & schedule Confidence Limit (JCL)

April 25, 2011


April 22, 2011


April 28, 2011

March 2011

Complete flight ISIM Remote Services Unit Thermal Vacuum testing


Deliver Fine Guidance Sensor (FGS) test unit electronics to ISIM Integration & Test


Complete 2018 Launch Readiness Date budget details

February 19, 2011, Completed one month early

February 24, 2011, Completed one month early

April 7, Completed one week late

February 2011

Deliver Near-Infrared Spectrograph flight spare detector to GSFC


Pathfinder Primary Mirror Backplane Support Structure delivered to Northrop-Grumman Aerospace Sys.


Establish No-Earlier-Than Launch Readiness Date as part of replan

Establish Work Breakdown Structure for new GSFC responsibilities

January 29, 2011, Completed one month early

March 25, 2011, Completed one month late (weather conditions affected shipping)

February 25, 2011


February 28, 2011

January 2011

Ship Mid-Infrared Instrument (MIRI) Focal Plane Electronics to ESA (Rutherford Appleton Lab.)

Ball's Flight Actuator Drive Unit Software Test Review

January 20, 2011


January 24, 2011

 

 

 

 

Spacer
NASA Home 
Page ESA Home 
Page CSA Home 
Page

Webmaster: Maggie Masetti

Responsible NASA Official: John Durning

+Privacy Policy and Important Notices

Spacer
Spacer Spacer Spacer