Recent Accomplishments
Updated February 6, 2013
The following list contains a record of program and project
accomplishments for the James Webb Space Telescope. The left column gives the original due date, the middle column gives the item accomplished, and the right column indicates the
schedule performance with green text denoting items accomplished earlier than
planned, black text for items completed on schedule, and red text for items
finishing later than planned. The list will be updated approximately every
month.
The image below points out various
major hardware components of the facility referred to in the list to orient the
reader. (Click to enlarge image.)
Due Date
Item Accomplished
Completion Date
Secondary Mirror Support Structure I&T tooling fixture complete
Primary mirror backplane support wing assemblies complete
Spacecraft Primary Structure Manufacturing Readiness Review
Start cryogenic certification test of OSIM
January 28, 2013
Moved to March 2013 - delayed by Global Precipitation Monitor exit from SES chamber
Aft optical system complete
Receive JWST carrier container to be used in moving the observatory to testing and launch sites
System design review of the software employed in managing all the data returned from the spacecraft to the operations center
Deliver MIRI cover/thermal shield to ISIM integration and test (I&T;)
January 10, 2013
November 16, 2012
December 6, 2012
Dynamics and Thermal issue have delayed delivery to March, Two weeks of schedule margin still exists to need date
First engineering model of the spacecraft command and telemetry computer delivered to test bed
Reinstall beam image analyzer onto telescope simulator (OSIM) used in ISIM cryogenic testing
Complete electrical checkout of combined fine guidance sensor (FGS) and ISIM
November 8, 2012
December 19, 2012
December 20, 2012
Spacecraft-to-Optical Telescope Element/science instruments stray light and thermal barrier structures preliminary design review
Port side spacecraft equipment panel design review (Northrop internal review)
Complete electrical checkout of combined mid-infrared instrument (MIRI) and integrated science instrument module (ISIM)
October 18, 2012
October 4, 2012
November 19, 2012. 2 days of testing required in Jan. due to FSW bug (divide by zero)
Headquarters delivery to project of funding plan for fiscal 2013
Spacecraft batteries preliminary design review
Spacecraft command & telemetry computer review (Northrop internal review)
Second review of optical test equipment for Johnson Space Center (JSC) thermal vacuum chamber test of telescope and instruments (OTIS)
September 15, 2012
September 6, 2012
August 30, 2012
October 17, 2012
Deliver NIRCam
Start testing of cryogenic camera system, used for subsequent JSC I&T;
Complete center section of Backplane Support Structure for main mirror
Deliver NIRSpec
Moved to no earlier than 12/2012, work around in place
Delivery no later than August 2013
August 9, 2012
April 28, 2012
Delivery date April 2013Delivery no later than September 2013
Order remaining JSC thermal vacuum chamber vibration isolators
Deliver Flight Fine Guidance Sensor
Deliver flight software to ISIM Integration and Testing ("ISIM I & T")
Complete Solar array Preliminary Design Audit
Deliver MIRI Cryo Cooler "Cold Head Assembly" (critical component of MIRI cooling) to ISIM I&T
Complete fabrication of end fitting for Secondary Mirror Support Structure
July 30, 2012
May 11, 2012
June 14, 2012
Flight CHA to be delivered in June 2013. No schedule, impact, work around in place.
July 13, 2012
June 30, 2012
June 13, 2012
June 21, 2012
June 28, 2012
Finish testing the COCOA
Measure Sunshield template layer 5 shape to confirm its accuracy
Conduct budget and schedule review of replanned program and project performance
March 9, 2012
April 23, 2012
May 30, 2012
Complete all composite parts for mechanism that lifts telescope away from spacecraft after launch (Deployable Tower Assembly)
Receive MIRI from Europe (extra vibration test delay)
February 28, 2012, completed two months early
May 29, 2012
Deliver ISIM computer #2 to ISIM integration and testing. (Single synchronous dynamic random access memory chip failure during computer thermal vacuum testing. Chip is being replaced and computer retested. )
Complete analysis of JSC Thermal Vacuum Chamber telescope testing equipment plans
System Engineering Team to complete assessment of instrument thermal margins
Delivery of 2nd ISIM computer to Integration and Test
May 15, 2012
March 19, 2012
March 1, 2012
May 16, 2012
February 2, 2012, (all panels, walls, floor, ceiling, door)
December
19, 2011, Completed two months early
December
15, 2011, Completed one month early
January
19, 2012
December
1, 2011, Completed one month early
December 2, 2011, Completed
one month early
Install
Helium shroud floor at Johnson Space Center thermal vacuum chamber ("JSC
TVC")
Determine
root cause of NIRSpec optical bench flaw
October
27, 2011 Completed two months early
December
15, 2011
Complete
electronics simulator model for Integrated Science Instrument Module ("ISIM")
Deliver
tools for software development environment and verification
November 15, 2011
October,
27, 2011 Completed one month early
Deliver
Flight ISIM Electronics Compartment to ISIM Integration & Test
Deliver
flight ISIM Command & Data Handling unit #1 to ISIM Integration & Test
August 2012
September
27, 2011
Spacecraft
Flight Software Build 1 Technical Readiness Review
June 30, 2011, Completed
two months early
Deliver
ISIM Region 1 Wiring Harnesses
Deliver
ISIM Structure to ISIM Integration & Test
July 22, 2011
July 28, 2011
Complete
Common Command & Telemetry System Build 2.3
Start
ISIM level Integration & Test
April 13, 2011, Completed
two months early
June 24, 2011
Start
flight Fine Guidance Sensor environmental testing (instrument level)
Complete
Spacecraft Secondary Mirror Segment Cone Structure internal Design Review
May 5, 2011
April 20, 2011 Completed
one month early
Pathfinder
Primary Mirror Segment Assemblies complete
Deliver
ISIM Command & Data Handling test unit to ISIM Integration & Test
Complete
2018 Launch Readiness Date project lead Joint cost & schedule Confidence
Limit (JCL)
April 25, 2011
April 22, 2011
April 28, 2011
Complete
flight ISIM Remote Services Unit Thermal Vacuum testing
Deliver
Fine Guidance Sensor (FGS) test unit electronics to ISIM Integration &
Test
Complete
2018 Launch Readiness Date budget details
February 19, 2011,
Completed one month early
February 24, 2011,
Completed one month early
April 7, Completed
one week late
Deliver
Near-Infrared Spectrograph flight spare detector to GSFC
Pathfinder
Primary Mirror Backplane Support Structure delivered to Northrop-Grumman
Aerospace Sys.
Establish
No-Earlier-Than Launch Readiness Date as part of replan
Establish
Work Breakdown Structure for new GSFC responsibilities
January 29, 2011, Completed
one month early
March 25, 2011, Completed
one month late (weather conditions affected shipping)
February 25, 2011
February 28, 2011
Ship
Mid-Infrared Instrument (MIRI) Focal Plane Electronics to ESA (Rutherford Appleton
Lab.)
Ball's
Flight Actuator Drive Unit Software Test Review
January 20, 2011
January 24, 2011
|
|
|