Click the Play Button on the bottom left of the video to start the playback. Alternatively, view on YouTube.
PHOTO GALLERY
Click thumbnail images for larger view
South side of Route 5: New abutment (left) and existing abutment (right). New #1 abutment Stem (Forground),#3 Abutment Form (Background).
North side of Route 5: Panoramicview Abutment 4 (left), Falsework Towers (Right) that will serve as temporary supports to new bridge superstructure while it is being built.
North side of Route 5: Panoramicview Abutment 4 (left), Falsework Towers (Right) that will serve as temporary supports to new bridge superstructure while it is being built.
Surveying Falsework Towers
Beams for Northbound bridge installed over Route 5
Deck panels for Northbound Bridge over Route 5
Deck panels for Southbound Bridge over Route 5
A retaining wall footing is being poured, using a crane and concrete bucket to transport concrete from truck to forms.
Backfilling Southbound (south side of Route 5) abutment.
Pouring (concrete) on the precast deck panels supports on top of girders
Tying rebar on the Northbound bridge deck
Pouring concrete for retaining wall
This photo shows deck pouring of the approach slabs in the median.
Concrete is lifted from a truck on Route 5 for pouring the Northbound deck overhead.
Crew stands on rebar that will be covered with concrete once the pour is done.
Pouring concrete is complete.
Pouring concrete on approach slab.
Barrier wall for North bound bridge.
Concrete is poured over rebar on southbound bridge deck.
Concrete is pushed up from trucks on Route 5.
Bridge pour for southbound bridge deck is almost complete.
Aerial view #1
Aerial view #2
I-91 is closed to traffic at 6 p.m. Friday, August 31
Sawcutters make first cut to remove existing highway bridge.
Sparks fly as bridge railing is removed.
Several sawcutters cut through the bridge deck simultaneously.
A slab of from the center of the bridge is removed by crane. Crews worked through the night and into the next day removing the old bridge.
The south bridge pier is pulled over.
Mid-afternoon on Saturday, August 29, hydraulic jack (yellow) is used to push the bridge in about five hours.
PCL construction worker wiping the surface of the slide beam, making sure there is no friction to slow the slide.
VTrans Secretary Sue Minter explains construction project to spectators.
North approach slab is lowered into place on Sunday afternoon,
August 30.
Crew bonds approach slabs together. Once done, paving can begin.
Paving begins Sunday evening. Bridge opens at 3:00 a.m. on Monday,
August 31
Trial slide of Southbound bridge – Sunday, Sept 13
Trial slide of Southbound bridge – Sunday, Sept 13
I-91 Southbound closes Friday, Sept 18; flaggers assist motorists with directions all weekend
Demolition of bridge begins Friday evening
Hoe ram pries concrete and rebar from bridge beam
View of Southbound bridge Friday evening
Southbound bridge gone by Saturday morning,
Sept 19