Schedule & Calendar

  • Summer and Fall 2016: Install conduit for utility relocation, install drainage and retaining wall
  • Fall 2016 to Late Spring 2017: Relocate utilities – work will be performed by telecommunications and electrical companies
  • Summer to Fall 2017: Advertise and award construction contract, build access roads and support piers and abutments
  • 2018: Majority of bridge and roadway construction occurs